Guideline F-09

Question

Answer

No.

According to Annex I Section 3.1.3 the PED requires qualification for NDT personnel that carry out NDT of permanent joints. No accreditation is required for the manufacturer’s NDT or DT laboratory or for the testing laboratory that the manufacturer may subcontract for NDT or DT.